RMT example lorry loader plan drawing: the vehicle at its standing, stabiliser spreads, slew paths, farthest reach and the exclusion zone
Lorry LoaderHS2 main works sites

Lorry Loader Plans Rewritten for HS2

A tyre-fitting specialist needed its lift plans brought up to the standard the tier 1 joint venture reviews against. Both plans are now accepted and in use on HS2 sites.

Project
HS2 main works civils
Client
Tyre-fitting specialist (name withheld)
Principal contractor
Tier 1 joint venture
Machines
HMF 3000 K5 on a 32 t rigid; Hyva HA 22 E3 on a 3.5 t van
Loads
Earthmover tyres up to 600 kg
RMT role
Lift plans and Appointed Person
RMT example lorry loader plan drawing: the vehicle at its standing, stabiliser spreads, slew paths, farthest reach and the exclusion zone
Our public example lorry loader plan drawing. This job's own drawings follow the same standard but carry the client's details, so they are not shown.
The Brief

Plans that would stand up to a tier 1 review

The client services the tyres on earthmoving plant across HS2 sites. Tyres up to 600 kg are removed, handled and refitted using two vehicle-mounted cranes: a knuckle-boom loader crane with a hydraulic tyre handler on a 32 t rigid, and a smaller loader crane on a 3.5 t service van.

Their existing lift plans needed rewriting to the standard the joint venture running the works reviews against before the work could carry on. We rewrote both plans from the ground up and acted as Appointed Person.

The Plans

What we put in them

A tier 1 reviewer checks a lorry loader plan against the right standard, the manufacturer's data and their own site rules. We wrote to all three.

One plan per vehicle and crane, restricted to that machine and configuration, so nobody can borrow a plan for a crane it was not written for

BS 7121-4 (lorry loaders) as the governing standard, with ALLMI’s code of practice and lift planning method

The joint venture’s own vehicle immobilisation and release standard and its approved cards guidance, written into the safe system of work

A generic plan for a repetitive lift with a purpose-built attachment, as BS 7121-4 allows, stepping up to an Intermediate lift and back to the Appointed Person when the pre-lift check finds an overhead line, an excavation, a slope or any other proximity hazard

Duties read from the manufacturers’ published duty charts for each crane

Ground bearing under the stabiliser mats checked by the ALLMI method

Elevation and plan drawings to scale, the manufacturers’ data, COSHH, a risk assessment, pre-lift verification hold points and a briefing sheet

A six-month review date, or sooner on any change of machine, attachment, load or method

The Numbers

Two cranes, two governing lifts

Truck-mounted crane

HMF 3000 K5 knuckle-boom on a 32 t 8×4 rigid, with a hydraulic tyre handler. Governing lift: a tyre up to 600 kg plus the handler, 1,390 kg in all, at 12.0 m radius: 81.8% of the published duty against a 90% ceiling. Ground bearing 179 kPa against 200 kPa allowable on 1.0 m mats.

Van-mounted crane

Hyva HA 22 E3 on a 3.5 t service van, lifting tyres with a bead hook. Governing lift: a tyre up to 545 kg at 2.31 m radius on the first hydraulic extension: 73.5% of the published duty against a 90% ceiling.

Written to be reviewed

Each plan carries our 19-point assurance map and sets out the hold points the lift team must close on the day, before the first lift.

Outcome

Accepted and in use on HS2

Both plans were accepted by the joint venture and are in use on HS2 sites. Because each one is generic for its vehicle but tells the lift team exactly when to stop and call the Appointed Person, the client can work across sites without a new plan for every visit.

We write lorry loader lift plans to BS 7121-4 and ALLMI for HIAB, loader crane and van-mounted crane operators, and review lift plans for principal contractors. There is more on how we work in our software and drawings.

Lorry loaderVan-mounted craneHS2Tier 1 joint ventureBS 7121-4ALLMILOLER 1998

The client and the joint venture are not named. Figures are taken from the issued lift plans. The drawing shown is one of our public examples, not this job.