RMT example drawing: a midi excavator lifting from the quick-hitch lifting eye with the bucket off, radius and heights marked
ExcavatorWastewater treatment works, Lancashire

Rising Main Excavator Lifts

One lift plan for three possible machines, nine lift types and welded pipe strings, revised twice in six days as the site changed, and reissued on the start date.

Project
135 m of 400 mm PE rising main
Site
Wastewater treatment works, Lancashire
Client
Pipeline contractor (name withheld)
Machines
JCB 85Z-2, 86C-2 or 90Z-2
Lifts
9 lift types, up to 1,268 kg
RMT role
Lift plan and Appointed Person
RMT example drawing: a midi excavator lifting from the quick-hitch lifting eye with the bucket off, radius and heights marked
Our public example excavator drawing. This job's own drawings follow the same standard but carry the client's details, so they are not shown.
The Brief

Pipe laying with whichever midi excavator turned up

A pipeline contractor working for a principal contractor at a wastewater treatment works was laying about 135 m of 400 mm PE100 rising main in trenches dug by others. The pipe was butt-fusion jointed into strings, with blank flanges at each end. A midi excavator would unload the pipe, the fusion machine, the generator and the fittings, carry them to the weld station, and lower the welded strings into the trench.

The contractor did not know which machine the hire company would send: a JCB 85Z-2, 86C-2 or 90Z-2. We wrote the lift plan and acted as Appointed Person, to CPA CIG 0801 (excavators used as cranes), BS 7121-1 and LOLER 1998 regulation 8.

The Plan

What the plan covered

A plan written to be used on the bank, not filed. Every figure traces back to the manufacturer's published data and the certificates for the kit on site.

One plan for all three midi excavators the hire company might send, with every lift checked on each machine over the side through 360° and over the front, and the reach and height left over

Every load built up from the item, the lifting accessories and the quick hitch. Heaviest total load 1,268 kg; highest utilisation 65.5% of the manufacturer’s chart against an 80% ceiling

Welded pipe strings: what the machine really lifts when a string is picked, and a quick-hitch eye rated at least 1,200 kg because a string pick hangs 1,173 kg from it

The bucket off for every lift, with loads lifted from the rated quick-hitch lifting eye only

Pick and carry limited to 50% of the blade-up chart

A register of the lifting accessories on site and six rigging sets drawn as the actual kit, each with its certificate

Ground, trench and temporary works, exclusion zones, environmental controls and COSHH for diesel and hydraulic oil

Hold points to close before the first lift, daily pre-use checks and a briefing record for the lift team

A3 drawings in the order of the job: unloading, moving to the weld station and lifting into position

Changes on Site

Three revisions in six days

Sites change, and a lift plan has to keep up. Each change was worked through the figures and the drawings, not just noted, so the plan on the bank always matched the kit and the people actually there.

Rev A · 20 October

First issue for use, covering all nine lift types on any of the three machines.

Rev B · 23 October

After the site review: confirmed no spreader beam, lifting beam or roundsling would be used, and took the bucket off for every lift. Loads, utilisation, ground bearing and drawings were all recalculated.

Rev C · 26 October

Issued on the start date, after the contractor changed its lifting kit and lift supervisor. Accessory register, rigging sets and certificates redone; lifts extended to 360° and over the front; drawings redrawn as a sequence.

Outcome

Every lift completed safely

The work went ahead on the Rev C plan and every lift was completed safely. Because the plan already covered all three machines and every lift in both directions, the contractor could start with whichever excavator arrived, without waiting for a rewrite.

We write excavator lift plans for pipeline, utilities and groundworks contractors across the UK, and act as their Appointed Person where they have none of their own. There is more on how we work in our software and drawings.

ExcavatorPipe layingWater industryWelded PE stringsCPA CIG 0801BS 7121-1LOLER 1998

Client, principal contractor and site names are withheld. Figures are taken from the issued lift plan. The drawing shown is one of our public examples, not this job.

Got an excavator lift coming up?

Send us the job, the machines and the loads. Fixed price, quoted within four working hours.

Discuss Your Project
Call RickyWhatsApp