When forklift work needs a written lift plan
A forklift lifting or lowering a load is lifting equipment under LOLER 1998, and every lifting operation has to be properly planned by a competent person. For a routine pallet move that planning is usually the employer's risk assessment and safe system of work. A specific written lift plan is needed when the job is out of the ordinary: a heavy or awkward load, a load whose centre of gravity is not where the capacity plate assumes, an attachment that changes the truck's rating, or ground and floors that may not take the weight.
A forklift is not a crane, so we do not apply BS 7121 lift categories to forklift work. Our forklift plans are built on LOLER 1998, the ACOP L113 on safe use of lifting equipment, ACOP L117 on rider-operated lift trucks and the manufacturer's instructions for the truck and its attachments.
Machinery and equipment moves
Presses, CNC machines, generators, transformers and plant, where the weight and centre of gravity have to be confirmed before anything is lifted.
Loading and unloading vehicles
Delivery bays and site deliveries: driver safe area, vehicle stability, load shift and pedestrian segregation.
Fork-mounted jibs and hooks
Suspended loads on a forklift, with the combined truck and jib capacity, slinging and tag-line control planned in.
Long and offset loads
Steel, timber, pipe and precast where the load centre sits further out than the capacity plate assumes.
Suspended floors and mezzanines
Front-axle loads checked against the floor, slab, ramp or dock leveller the truck will cross.
Principal contractor request
When the main contractor wants a written lift plan in the RAMS package before the truck starts work.
What's in your forklift lift plan
One complete pack, signed off by a CPCS Appointed Person and ready for your RAMS file.
Truck and attachment verification
- Make, model and capacity plate checked against the attachments fitted
- Thorough examination report covering mast, chains, forks and attachments
- Fork rating, fork extensions and their limits
- Jib or hook attachment SWL and combined capacity, where used
- Operator training, familiarisation and authorisation
Load and capacity
- Load weight from a reliable source, never an unchecked estimate
- Centre of gravity and actual load centre
- Capacity at that load centre and lift height, from the manufacturer’s data
- Utilisation against the limit for the job
- Lifting accessories schedule for jib work
Route, floor and ground
- Route surface, gradients and turning space
- Suspended floors, mezzanines, ramps and dock levellers
- Overhead clearances: doors, beams, sprinklers and cables
- Pedestrian segregation in straight barrier runs
- Vehicle loading arrangements where needed
Documentation pack
- Scale drawings of the route, pick and place positions
- Risk assessment listing every hazard and its controls
- Method statement with the sequence of operations
- Emergency procedures and briefing record
- PDF ready for principal contractor review
The capacity plate is only the start
A forklift's rated capacity holds only at the load centre on its plate, with the mast vertical, on firm level ground and with the attachment the plate was issued for. Change any of those and the safe capacity changes. We take every figure from the manufacturer's data for that exact truck and attachment, never from a rule of thumb.
What changes the capacity
| Standard forks, load at plate load centre | Per capacity plate |
| Load centre further out (long or offset load) | Reduced: load-centre chart |
| Fork extensions | Reduced: maker’s data |
| Clamp, rotator or positioner | Per combined plate |
| Fork-mounted jib or hook | Jib SWL at the hook position used |
| Lifting to full mast height | May be reduced at height |
Every forklift plan we write checks:
- That the capacity plate matches the attachment actually fitted
- The real load centre, measured from the fork face to the centre of gravity
- Capacity at the lift height needed, not just at ground level
- Front-axle load against any floor, slab or ramp on the route
- Gradients: loads carried on the uphill side, no turning on slopes
Operators, examinations and the rules that apply
Forklift operator
A16 for industrial counterbalance trucks, A14 for rough-terrain masted trucks, or NPORS, RTITB, AITT or ITSSAR-accredited training. Plus job-specific training, familiarisation and written authorisation (ACOP L117).
Thorough examination
Lifting chains, forks, mast and attachments examined at least every 12 months, or as a written scheme of examination sets out.
Safety inspection
Brakes, steering, tyres and the other safety items inspected under PUWER, alongside the LOLER examination.
Slinger / signaller
For fork-mounted jib work, the load is slung and released by a trained slinger/signaller (or NPORS equivalent). Accessories examined every 6 months.
Lifting people: never on the forks, on a pallet or in a loose cage. HSE guidance allows a non-integrated working platform on a forklift only in exceptional circumstances. For work at height, plan a MEWP instead.
How it works and how fast
From £200 + VAT, fixed fee. Each lifting device gets its own plan, so a job that uses a forklift and a crane gets two plans, each one clear enough to brief from.
You send the brief
Truck make and model, attachment, load weight and dimensions, photos, and a sketch or drawing of the route, pick and place.
We quote
Fixed-fee quote within 4 working hours, with the scope and delivery date confirmed.
Plan produced
Capacity check, drawings, risk assessment and method statement prepared by a CPCS Appointed Person.
Briefing and sign-off
Plan issued as a PDF. We answer reviewer queries from your principal contractor.
Writing it yourself? Use our free template
Our free forklift lift plan template in Word covers the capacity check, route and floor checks, vehicle loading, hazards, method statement and briefing record.
Already got a plan? We'll check it.
Independent Appointed Person review of a subcontractor's forklift lift plan: capacity at the real load centre, attachments, floor loading, segregation and method.
Forklift lift plan FAQs
Does a forklift need a lift plan?
LOLER 1998 requires every lifting operation to be properly planned by a competent person, and a forklift lifting or lowering a load is lifting equipment under LOLER. A routine pallet move is normally covered by the employer’s risk assessment and safe system of work. A specific written lift plan is needed when something about the job is out of the ordinary: a load near the truck’s capacity, an offset centre of gravity, a machinery move, a fork-mounted jib, a lift over a suspended floor, or a principal contractor who asks for one.
Does LOLER apply to forklift trucks?
Yes. When a forklift lifts or lowers a load it is lifting equipment under LOLER 1998, and it is also work equipment under PUWER 1998. HSE treats the two sets of regulations as applying together: LOLER for the lifting parts, PUWER for safety items such as brakes, steering and tyres.
How often does a forklift need a thorough examination?
HSE guidance is that the lifting chains, forks, mast and cylinders and fork attachments are thoroughly examined at least every 12 months, or at the intervals set by a written scheme of examination. Lifting accessories, such as slings used with a fork-mounted jib, are examined every 6 months. Equipment used to lift people is also examined every 6 months.
Which card does a forklift operator need?
There is no single legal card. CPCS A16 covers industrial counterbalance forklifts and CPCS A14 covers rough-terrain masted forklifts; NPORS, RTITB, AITT and ITSSAR-accredited training are also widely accepted. ACOP L117 expects three stages of training (basic, specific job and familiarisation on the truck being used) and the employer’s written authorisation to operate. Check what the principal contractor accepts on site.
Can a forklift lift a suspended load?
Only with a fork-mounted jib or hook attachment designed for it, examined, secured to the truck as the manufacturer specifies, and used within the combined capacity for that truck and attachment. The load must be slung by a trained slinger/signaller, controlled with tag lines and kept low. The capacity is usually well below the truck’s fork rating, so it must be taken from the manufacturer’s data, never assumed.
Can people be lifted on a forklift?
Never on the forks, on a pallet or in a loose cage. HSE guidance allows a non-integrated working platform on a forklift only in exceptional circumstances. In almost every case a MEWP is the right machine for working at height.
If the job uses a forklift and a crane, does each need its own plan?
Yes. Each lifting device gets its own lift plan, because each machine has its own capacity, set-up and hazards. A single plan covering several machines is hard to read on site and is routinely rejected by principal contractors.
How much does a forklift lift plan cost and how quickly can I have it?
Forklift lift plans start at £200 + VAT, fixed price. We quote within 4 working hours and normally deliver within 24–48 working hours of receiving the full job information. Plans are written remotely from the information you send: the truck make and model, the load weight and dimensions, photographs and a sketch or drawing of the route.
Get a quote for your forklift lift plan
07803 8080933 fields, 30 seconds. We reply within 4 working hours.
Related services
Most projects need more than one of these. Here's what often pairs with this service.
Telehandler Lift Plans
Suspended-load lift plans for telescopic handlers on hook duties. CPCS A77C compliant.
Learn moreOverhead & Gantry Crane Lift Plans
Lift plans for overhead travelling (EOT), gantry, bridge and jib cranes in factories and warehouses. BS 7121-7 compliant.
Learn moreLift Plan Writing
LOLER compliant lift plans for excavators, telehandlers, mobile cranes and lorry loaders. 24-48 hour turnaround.
Learn moreSend the brief, get the plan
From £200 + VAT, fixed fee. We'll come back to you the same working day.
What we need from you:
- • Site address and a sketch or drawing of the route
- • Forklift make and model, and any attachment fitted
- • Load weight, dimensions and centre of gravity if known
- • Photos of the load, the truck's capacity plate and the route
- • Floors, ramps or vehicles involved
- • Date of the operation