Steel erection lift plan example: a mobile crane erecting a steel frame

Part 2 of the steel delivery example: a 3D view from an RMT Solutions steel erection lift plan (example job). A Liebherr LTM 1090-4.2, working over the side, lifts a UB 406x178x60 on two load rings through its top flange from the telehandler’s staging point into the next bay of a steel frame in progress, at 17.3% utilisation of the Liebherr duty chart.

The video is rendered from the same 3D model as the plan's drawings, so the machine, the radius and the load match the figures on the sheets.

The lift in figures

Crane
Liebherr LTM 1090-4.2, working over the side, outriggers on mats
Configuration
30.0 m main boom, 22.5 t counterweight
Load
UB 406x178x60, 7.0 m, 421 kg
Rigging
Two RUD VLBG-PLUS M20 load rings through the top flange at 200 mm centres, 2-leg chain with 3 m legs
Gross load
760 kg including the rigging and the hook block
Duty
4.4 t on the Liebherr chart at the 24 m landing radius
Utilisation
17.3%

Utilisation is the gross load, including all the lifting accessories, divided by the capacity on the manufacturer's chart for that configuration and radius.

What the video shows

  1. 0:00Part 2: from the telehandler’s staging point, drawn from an RMT steel erection lift plan
  2. 0:05The crane: Liebherr LTM 1090-4.2 over the side, 30.0 m main boom, 22.5 t counterweight, outriggers on mats
  3. 0:10The duty check: 760 kg gross against 4.4 t at the 24 m landing radius, 17.3% utilisation
  4. 0:16Two RUD VLBG-PLUS M20 load rings through the top flange at 200 mm centres, 2-leg chain with 3 m legs
  5. 0:21Into the next bay of the frame: lift supervisor and slinger / signaller
  6. 0:28Lift plans by a CPCS A61 Appointed Person
Watch the vertical version on YouTube Shorts

Every RMT lift plan comes with drawings like these