Telehandler lift plan example: steel from the wagon to the crane, stage by stage

A 3D view from an RMT Solutions telehandler lift plan (example job). A JCB 540-170 on forks moves 2 x UB 406x178x60 at 7.0 m (841 kg) off the delivery vehicle, onto the steel laydown and then to the staging point inside a Liebherr LTM 1090-4.2’s 16 m reach.

The video is rendered from the same 3D model as the plan's drawings, so the machine, the radius and the load match the figures on the sheets.

The lift in figures

Telehandler
JCB 540-170 on forks, working on its tyres
Load
2 x UB 406x178x60 at 7.0 m: 841 kg
Reach
2.0 m from the front tyre face
Capacity
JCB rates 1,000 kg out to 5.68 m reach on tyres
Stages
Off the delivery vehicle, to the steel laydown, to the crane’s staging point
Crane
Liebherr LTM 1090-4.2: 16 m reach, 6.7 t at 16 m on its duty chart

What the video shows

  1. 0:00The steel delivery in 3D, drawn from an RMT telehandler lift plan
  2. 0:05Stage 1: a JCB 540-170 on forks lifts 2 x UB 406x178x60 (7.0 m, 841 kg) off the delivery vehicle
  3. 0:13Stage 2: set down on the steel laydown, layer on layer on timber bearers
  4. 0:19The capacity check: 841 kg at 2.0 m from the front tyre face, inside JCB’s 1,000 kg out to 5.68 m on tyres
  5. 0:26Stage 3: to the crane’s staging point, barrier runs closed and the banksman in sight of the operator
  6. 0:32Ready for the crane: inside the LTM 1090-4.2’s 16 m reach, 6.7 t at 16 m on its chart
  7. 0:38Lift plans by a CPCS A61 Appointed Person
Watch the vertical version on YouTube Shorts

Every RMT lift plan comes with drawings like these

An elevation, an exclusion zone plan, a rigging drawing and 3D views, drawn to the machine's real dimensions and written by a CPCS A61 Appointed Person with 35 years in lifting operations.

Example job for illustration. It is not a site instruction or an approved plan for another lift: every lift needs a plan for the actual machine, load and site.